2018

Saxony - Brandenburg

3 Days

Prof. Dannewitz, Prof. Wiese

  • UVR-FIA GmbH Freiberg
    • Research and development in the field of applied mechanical process engineering
  • Waste incineration plant "EEW Energy from Waste" Großräschen
    • Thermal waste utilisation with a capacity of 260,000 t/a
    • Power generation 175,000 MWh/a, district heating
    • Multistage flue gas cleaning
  • Lignite-fired power plant "Schwarze Pumpe"
    • Generation of process steam, district heating and electrical energy from raw lignite
    • Flue gas cleaning with electrostatic precipitator, denitrification and desulphurization
  • MBA Cröbern and ZDC
    • Mechanical biological waste treatment 300,000 t/a
    • Central landfill with basic sealing, control and service tunnel, gas collection and gas utilisation, leachate treatment, surface sealing
  • Scholz-Recycling/SRW metalfloat GmbH Espenhain
    • End-of-life vehicle recycling
    • Processing of shredder light and heavy fraction and plastics

Year

Target

Duration

Line

2011

Hamburg-Berlin-Dresden

6 Days

Prof. Schade-Dannewitz, Dr. Parnieske-Pasterkamp

  • Inspection of the warehouse district and harbor city in Hamburg
  • IBA Wilhelmsburg
  • Wwaste incineration plant "Rugenberger Damm" Hamburg
    • Projected capacity 320000 t/a
    • Generation of process steam, district heating, electricity
    • Waste gas purification with gypsum and HCl production
  • "MEAB Potsdam, Schöneiche" waste disposal site
    • Landfill with combined heat and power plant
    • Mechanical-biological waste treatment plant
    • Hazardous waste incineration plant
  • Lignite-fired power plant "Schwarze Pumpe"
    • Generation of process steam, district heating and electrical energy from raw lignite
    • Flue gas cleaning with electrostatic precipitator, denitrification and desulphurization
  • UVR-FIA GmbH Freiberg
    • Research and development in the field of mechanical process engineering

Year

Target

Duration

Line

2007

New Federal States and Berlin

4 Days

Prof. Schade-Dannewitz

  • MPS Betriebsführungsgesellschaft Berlin-Pankow
    • Mechanical-physical stabilization plant of residual waste
    • Production of substitute fuels
  • Brandenburg University of Technology Cottbus
    • Faculty of Environmental Sciences and Process Engineering
  • Lauta thermal waste treatment plant
    • Waste incineration plant with moving grate and SCR flue gas cleaning
    • Throughput 240,000 t/a
    • electricity is generated from the waste
  • German Solar AG Freiberg
    • Production of mono- and multicrystalline silicon wafers
    • Solar cell recycling

Year

Target

Duration

Line

2006

BKB Hannover

1 Day

Prof. Schade-Dannewitz

  • BKB Hanover
    • Waste incineration plant with moving grate and SNCR flue gas cleaning
    • Throughput 280,000 t/a
    • electricity and district heating are generated from the waste
  • AHA Waste Treatment Centre Hannover
    • Mechanical-biological residual waste treatment plant with dry fermentation
    • Throughput 240,000 t/a
    • Extraction of secondary raw materials such as metals and substitute fuels and biogas